HOLIDAY INN TABA

- Project Specifications:

Guest Rooms

The first phase of the project will consist of 178 guestrooms separated on 5 buildings.
Building A 16 guestrooms and 1 suite
Building B 60 guestrooms and 2 suites
Building C 48 guestrooms
Building D 24 guestrooms
Building E 24 guestrooms

Main Building

  • Basement area is 700 m2 and consists of:
    Refrigeration area and food storage
    Storage area for different purposes
    Loading dock and receiving area
    Staff kitchen and dinning
    Staff changing rooms
    Laundry


  • Ground floor area is 4,500 m2 and consists of:
    Reception lobby
    Lobby lounge
    Main restaurant
    Cafeteria
    Bar
    Multi purpose hall
    Shops
    Administration offices
    Business center
    Main kitchen and satellite kitchens
    Terraces overlooking the landscape, swimming pools and the sea


  • Mezzanine
    Consists of the rest of the administration offices.

Discotheque and Health Club Building

  • With a built up area of 1,300 m2 and consists of:
    Discotheque hall
    Hall for different sports
    Health center
    Reception
Swimming Pools:
  • With a total area of 1,800 m2 and consists of:
    Normal swimming pools
    Swimming pool of hot water
    Children swimming pool
  • Buildings of 500 m2 consists of:
    Cafeteria
    Bar
    Changing rooms
    Toilets

Landscape

  • Green areas of 100,000 m2
    Sports courts of 4,000 m2
    Beach restaurant of 350 m2
    Beach cafeteria of 120 m2

Water Tanks

  • Water tank of 400 m3
    Agriculture water tank of 550 m3

Remaining Works for The Taba Hotel:

PHASE 1

- Building A (Percentage of Completion is 90%)

1. Grouting and some finishing work for the roof.
2. Finishing of outside marble stairs.
3. Painting of the rooms.
4. Finishing of the marble vanity top for the bathrooms.
5. Doors for service rooms and ducts.
6. Expansion joints.
7. Some air conditioning split units to be installed.
8. Fire alarm units and panels are not installed.
9. Furniture for some rooms.
10. Out side walk ways.

- Building B (Percentage of Completion is 90%)

1. Grouting and some finishing work for the roof.
2. Finishing of outside marble stairs.
3. Painting of the rooms.
4. Finishing of the marble vanity top for the bathrooms.
5. Doors for service rooms and ducts.
6. Expansion joints.
7. Some air conditioning split units to be installed.
8. Fire alarm units and panels are not installed.
9. Furniture for some rooms.
10. Out side walk ways.
11. Painting of steelwork and handrails.

- Building C (Percentage of Completion is 85%)

1. Grouting and some finishing work for the roof.
2. Finishing of outside marble stairs.
3. Painting of the rooms.
4. Finishing of the marble vanity top for the bathrooms.
5. Doors for service rooms and ducts.
6. Expansion joints.
7. Some air conditioning split units to be installed.
8. Fire alarm units and panels are not installed.
9. Furniture for some rooms.
10. Out side walk ways.
11. Painting of steelwork and handrails.
12. Installing the elevator.

- Main Building (Percentage of Completion is 75%)

1. Roof insulation.
2. Finishing the air conditioning work.
3. Finishing and installment of kitchen, laundry and stores.
4. Finishing of fire alarm and fire fighting works.
5. Finishing of marble work.
6. Finishing of Cornish work.
7. Finishing of circular columns.
8. Finishing of internal painting work.
9. Finishing of false ceiling work.
10. Counters works.
11. Manufacturing of doors.
12. Finishing of aluminium work.
13. Decoration works.
14. Furniture works.
15. Out side finishing.

- Swimming Pool (Percentage of Completion is 95%)

1. Testing and commissioning.
2. Finishing of pool deck.
3. Finishing and installment of equipment for swimming pool bar.
4. Furniture.

- Landscape (Percentage of Completion is 90%)

1. Finishing of walkways.
2. Finishing of wooden works.
3. Finishing and installment of equipment for beach restaurant.
4. Beach works and furniture.
5. Finishing of fence and gate.

- Networks (Percentage of Completion is 85%)

1. Installment of some manholes covers.
2. Installment of some accessories.
3. Finishing of electromechanical rooms.
4. Testing and commissioning.
5. Finishing of roads

 

PHASE 2

- Building D & E (Percentage of Completion is 30%)

1. All works after Concrete and masonry works.